Oracle’s New Mexico AI Bet Faces a Delay Test

Oracle says its flagship New Mexico AI campus remains on track, but a force majeure notice has sharpened investor fears over permits, power infrastructure and the debt behind its vast data-center push.
Oracle’s New Mexico AI Bet Faces a Delay Test

Oracle’s New Mexico AI Bet Faces a Delay Test
Oracle’s Project Jupiter was meant to be a flagship of the Stargate AI infrastructure buildout: a New Mexico campus designed to provide 2.45 gigawatts of capacity and help turn the company’s swelling cloud backlog into revenue.

Instead, the project has become a test of whether the AI industry’s biggest promises can survive the slower realities of energy supply, permits and local resistance. Oracle sent a force majeure notice to Stack Infrastructure, a Blue Owl Capital-owned developer, preserving its right to delay payments if the campus misses its 2028 opening target. The company is not seeking to walk away as the main tenant, according to reporting on the notice.

Oracle’s public position is emphatic: “Project Jupiter remains on our planned schedule,” the company said, adding that it is “fully committed to New Mexico.” Blue Owl likewise said the notice “does not change the financial commitments to this multi-year project.”

But the protective legal step followed tangible setbacks. The gas pipeline intended to supply the fuel-cell-powered campus was delayed nearly six months, to February 1, 2027, after repeated permit denials. A separate air-quality permit remains pending, while residents and environmental groups have made the project a political flashpoint ahead of the midterms.

For investors, the issue is less whether a notice cancels a lease—it does not—than what it reveals about execution risk. Oracle shares fell about 4% to 5% after the news, while its long-dated debt and credit-default swaps showed renewed strain. RBC analyst Rishi Jaluria said the filing “signals the company’s own risk assessment on execution has shifted enough to warrant legal cover.”

Oracle counters that force-majeure notices are routine on projects of this scale and do not themselves alter delivery expectations. Yet with the company borrowing heavily to build AI capacity, even a modest slip in Jupiter’s 2028 timetable could postpone the revenue investors have been promised.