High Court Strikes Down Coal Mine Extension, Finds Climate Emissions Not Considered

Mine owner MACH Energy says it accepts the 3-2 decision but will 'actively pursue all available options' to ensure its long-term continuity.
High Court Strikes Down Coal Mine Extension, Finds Climate Emissions Not Considered

The High Court has derailed plans for a 22-year extension of the Mount Pleasant coal mine in NSW’s Hunter Valley. The court found that the company, MACH Energy, did not adequately consider the impact of emissions. This decision sends the matter back to the NSW Land and Environment Court for further consideration.

  • Plans for a 22-year extension of the Mount Pleasant coal mine have been stopped.
  • The High Court ruled the company did not properly consider the impact of emissions.
  • The case will return to the NSW Land and Environment Court.
  • MACH Energy is considering its options following the 3-2 verdict.